A heuristic approach for resource constrained project scheduling with uncertain activity durations

  • Authors:
  • M. E. Bruni;P. Beraldi;F. Guerriero;E. Pinto

  • Affiliations:
  • Universití degli Studi della Calabria, 87030 Rende (CS), Italy;Universití degli Studi della Calabria, 87030 Rende (CS), Italy;Universití degli Studi della Calabria, 87030 Rende (CS), Italy;Universití degli Studi della Calabria, 87030 Rende (CS), Italy

  • Venue:
  • Computers and Operations Research
  • Year:
  • 2011

Quantified Score

Hi-index 0.01

Visualization

Abstract

In this paper, we address the resource constrained project scheduling problem with uncertain activity durations. Project activities are assumed to have known deterministic renewable resource requirements and uncertain durations, described by independent random variables with a known probability distribution function. To tackle the problem solution we propose a heuristic method which relies on a stage wise decomposition of the problem and on the use of joint probabilistic constraints.