Robust optimization models for project scheduling with resource availability cost

  • Authors:
  • Denise Sato Yamashita;Vinícius Amaral Armentano;Manuel Laguna

  • Affiliations:
  • Departamento de Engenharia de Sistemas, Faculdade de Engenharia Elétrica e de Computação, Universidade Estadual de Campinas, CEP, Brazil 13083-970;Departamento de Engenharia de Sistemas, Faculdade de Engenharia Elétrica e de Computação, Universidade Estadual de Campinas, CEP, Brazil 13083-970;Leeds School of Business, University of Colorado, Boulder, USA 80309

  • Venue:
  • Journal of Scheduling
  • Year:
  • 2007

Quantified Score

Hi-index 0.00

Visualization

Abstract

We address a project scheduling problem with resource availability cost for which the activity durations are uncertain. The problem is formulated within the robust optimization framework, where uncertainty is modeled via a set of scenarios. The proposed solution method is based on the scatter search methodology and employs advanced strategies, such as dynamic updating of the reference set, a frequency-based memory mechanism, and path relinking. A multistart heuristic was also developed and comparative results are reported. The tradeoffs for risk-averse decision makers are discussed.