A genetic algorithm for the resource renting problem with minimum and maximum time lags

  • Authors:
  • Francisco Ballestín

  • Affiliations:
  • Department of Statistics and OR, Public University of Navarra, Pamplona, Spain

  • Venue:
  • EvoCOP'07 Proceedings of the 7th European conference on Evolutionary computation in combinatorial optimization
  • Year:
  • 2007

Quantified Score

Hi-index 0.00

Visualization

Abstract

We work with a project scheduling problem subject to temporal constraints where the resource availability costs have to be minimised. As an extension of the more well known Resource Investment Problem, which considers only time-independent costs, this problem includes both time-independent fixed costs and time-dependent variable renting costs for the resources. Consequently, in addition to projects where all resources are bought, we can deal with projects where resources are rented. Based on a new codification of a solution for project scheduling, we develop a Genetic Algorithm capable of outperforming a branch-and-bound procedure that exists for the problem.