A GRASP approach to transporter scheduling and routing at a shipyard
Computers and Industrial Engineering
Hi-index | 0.00 |
We characterize a nontrivial special case with a polynomial-time algorithm for a well-known parallel machine scheduling problem with precedence constraints, with a fixed number of machines, and with tasks of unit length. The special case is related to instances with given maximum path length and maximum degree of the task precedence graph. The method is based on the observation that the number of tasks is either small and bounded by a constant depending on the maximum path length and maximum degree, or alternatively, the number of tasks is large, giving a "dense" schedule.