General purpose simulation with stroboscope
WSC '94 Proceedings of the 26th conference on Winter simulation
Advantages of the activity scanning approach in the modeling of complex construction processes
WSC '95 Proceedings of the 27th conference on Winter simulation
Simulation of complex construction processes
WSC '96 Proceedings of the 28th conference on Winter simulation
Scalable simulation models for construction operations
WSC '96 Proceedings of the 28th conference on Winter simulation
Project scheduling using state-based probablistic decision networks
Proceedings of the 30th conference on Winter simulation
Construction of a dam embankment with nonstationary queues
Proceedings of the 31st conference on Winter simulation: Simulation---a bridge to the future - Volume 2
Who serves whom? dynamic resource matching in an activity-scanning simulation system
Proceedings of the 31st conference on Winter simulation: Simulation---a bridge to the future - Volume 2
Sequence step algorithm for continuous resource utilization in probabilistic repetitive projects
Proceedings of the 38th conference on Winter simulation
Optimal work breaks in deterministic and probabilistic repetitive projects
Proceedings of the 39th conference on Winter simulation: 40 years! The best is yet to come
Optimal scheduling of probabilistic repetitive projects using completed unit and genetic algorithms
Proceedings of the 39th conference on Winter simulation: 40 years! The best is yet to come
Hi-index | 0.00 |
Construction work is often performed with limited resources. The optimal dynamic allocation of resources at simulation runtime sometimes requires that non-critical tasks be held back deliberately and not be allowed to start so that resources will be available to perform more critical activities later. This is an important issue that has escaped rigorous investigation. For certain projects it may be more expedient to model work at the activity level and not the resource level and embed the routing of resources into precedence relationships. The Hanging Lake Tunneling Project is presented as an example where the estimation of tunnel advance rates for all tunneling alternatives is performed at the activity level and where the allocation of limited resources is encapsulated in tunneling plans particular to the tunneling alternative being analyzed.